NEDERLAND, TEXAS, Jan 22, 2014 (Marketwired via COMTEX) — TransCanada Corporation (TransCanada) announced today that at approximately 10:45 a.m. CST on January, 22, 2014, the Gulf Coast Project began delivering crude oil on behalf of our customers to Texas refineries. The completion of this US$2.3 billion crude oil pipeline provides a safe and direct connection between the important oil hub in Cushing, Oklahoma and delivery points on the U.S. Gulf Coast.
“This is a very important milestone for TransCanada, our shippers and Gulf Coast refiners who have been waiting for a pipeline to supply oil directly from Cushing,” said Russ Girling, president and chief executive officer. “This project is a critical, modern piece of American energy infrastructure that allows producers to safely connect growing production with the world’s most efficient refiners on the U.S. Gulf Coast. It also provides those American refineries the opportunity to use more of the crude oil produced in both Canada and the United States for decades to come.”
Construction of the 487-mile crude oil pipeline involved more than 11 million hours of labor completed by 4,844 workers in the United States of America, more than 50 contracts with manufacturers and companies building the pipeline and equipment from across the U.S. It also includes the addition of 2.25 million barrels of new oil storage capacity at Cushing, Oklahoma.
“The workers who helped build this project are in addition to 8,969 men and women who constructed the initial Keystone Pipeline system, and we are waiting for approval of Keystone XL so we can employ more than 9,000 more Americans who are waiting to put their skills and experience to work,” added Girling.
The Gulf Coast Project was designed to help relieve the glut of crude oil in places like Cushing, Oklahoma and will transport growing supplies of U.S. supply to meet refinery demand. It provides Gulf Coast refineries with access to lower cost domestic production and reduces America’s reliance on foreign sources of crude oil. In addition, the standards that TransCanada adopted for the Gulf Coast Project have set a new bar for safety and design of modern crude oil pipelines. This includes a higher number of remotely controlled shutoff valves, increased pipeline inspections, increased standards for pipeline construction, maintenance and integrity, and burying the pipe deeper in the ground.